Window treatments for all common areas

Estimate: $10,000

Porch railing – bring to code

Estimate: $7,500

Porch foundation – fix bowing

Estimate: $10,000

Windows

Estimate: $150,000
house_front_with_members_header.jpg

Phi Epsilon First! Building for the Future.

Projects

President’s bathroom – new supply lines, toilet and sink

Estimate: $5,000

Key projects and estimates.

Project
Estimate
Repair storage room and add new shelving (Prohibition Room)
$5,000
Locks & master keys
$5,000
Hallway doors
$10,000
Bedroom doors
$15,000
Window treatments for all common areas
$25,000
Furniture for all common areas
$25,000
Water filter system
$2,000
Room 34 roof leak
$5,000
Heating system – fix all radiators
$50,000
Kitchen – new appliances
$15,000
3rd floor bathroom – new vanity, lights, fan and shower doors
$5,000
2nd floor bathroom – new vanity, lights, fan and shower doors
$5,000
President’s bathroom – new water supply lines, toilet, and sink
$5,000
Strip & seal floors in all common areas
$5,000
Paint – all common areas on all floors
$15,000
Porch foundation – fix bowing
$10,000
Porch railing – bring to code
$7,500
Windows
$150,000
Egress windows – drainage issues
$20,000
Parking lot – regrade and blacktop
$50,000

Total: $429,500

Parking lot – regrade and blacktop

Estimate: $50,000